I got a couple items I wanted to pass along to everyone. First, if you are interested, there will be a kick-off celebration of the Measure M Bond Campaign (High School Bond Measure) on Monday, April 3, 2006 from 5:15 to 6:15 at The Monrovian restaurant, upstairs. Also, Clare Chesley sent me a budget of what will be done with the bond money, if it passes, and how much everything will cost. Feel free to pass it on to anybody who might be wondering what the money will go for.
~ brad@sacklunch.net
Here's how the district plans to spend the bond money:
MONROVIA UNIFIED SCHOOL DISTRICT
MONROVIA HIGH SCHOOL
AMENDED MASTER PLAN
March 8, 2006
SCIENCE BUILDING: $12,000,000
EXISTING SCIENCE BUILDING (14300sf @ $220/sf): $3,146,000
Complete Modernization
Tile Roof
Ceilings/lights
Move walls
Tech stations
White boards
Interior paint
Exterior sandblast & repair
HVAC
GYM New Facility: $8,000,000
STADIUM WITH CLASSROOMS: $1,800,000
TRACK & FOOTBALL FIELD: $2,700,000
TECHNOLOGY: $1,000,000
LIBRARY MEDIA UPGRADE: $350,000
Ceilings
Tech Area
ARTS BUILDING/UPGRADE: $2,150,000
BUILDING MODERNIZATION: $5,500,000
Hvac Upgrade
Ceiling/Lights
Exterior Sandblast/finish coat
Classroom flooring/hardware
Exit lighting/corridors
Auditorium - sound seating
MODERNIZATION OF SITE: $825,000
Drainage issues
Site work Friendship circle
Entry approach Building C
Marquee - signage allowance
Sub total: $37,471,000
20% Escalation: $7,529,000
TOTAL PROBABLE COST: $45,000,000
Also on the Web at www.monroviaschoollink.com
I got a couple items I wanted to pass along to everyone. First, if you are interested, there will be a kick-off celebration of the Measure M Bond Campaign (High School Bond Measure) on Monday, April 3, 2006 from 5:15 to 6:15 at The Monrovian restaurant, upstairs. Also, Clare Chesley sent me a budget of what will be done with the bond money, if it passes, and how much everything will cost. Feel free to pass it on to anybody who might be wondering what the money will go for.
~ brad@sacklunch.net
Here's how the district plans to spend the bond money:
MONROVIA UNIFIED SCHOOL DISTRICT
MONROVIA HIGH SCHOOL
AMENDED MASTER PLAN
March 8, 2006
SCIENCE BUILDING: $12,000,000
EXISTING SCIENCE BUILDING (14300sf @ $220/sf): $3,146,000
Complete Modernization
Tile Roof
Ceilings/lights
Move walls
Tech stations
White boards
Interior paint
Exterior sandblast & repair
HVAC
GYM New Facility: $8,000,000
STADIUM WITH CLASSROOMS: $1,800,000
TRACK & FOOTBALL FIELD: $2,700,000
TECHNOLOGY: $1,000,000
LIBRARY MEDIA UPGRADE: $350,000
Ceilings
Tech Area
ARTS BUILDING/UPGRADE: $2,150,000
BUILDING MODERNIZATION: $5,500,000
Hvac Upgrade
Ceiling/Lights
Exterior Sandblast/finish coat
Classroom flooring/hardware
Exit lighting/corridors
Auditorium - sound seating
MODERNIZATION OF SITE: $825,000
Drainage issues
Site work Friendship circle
Entry approach Building C
Marquee - signage allowance
Sub total: $37,471,000
20% Escalation: $7,529,000
TOTAL PROBABLE COST: $45,000,000